Information on temporary traffic management.

To apply for temporary traffic management on the highway please contact traffic@wolverhampton.gov.uk.

Traffic Management

Duration

Fees

Notification period

Lane closure

Emergency works

Nil

Within 2 hours

Planned works

Min. 7 working days

Temporary traffic control

Emergency works

Within 2 hours

Planned works (non-traffic sensitive routes)

7 working days

Planned works (traffic sensitive routes)

10 working days

Planned works at a junction

10 working days

Traffic signal switch off/on

Office hours (08:00 - 18:00 Mon - Fri)

£120.00 per visit

 

Out of hours and Saturdays

£400.00

Bank holidays and Sundays

£500.00

Temporary Traffic Regulation Order (TTRO):

Please note the cost incurred of any media advertising will be the responsibility of the applicant.

Road closure / TTRO up to 5 days and Public Right of Way closures

No more than 5 days

£750.00*

*plus advertisement cost of approx. £1100.00 - Please note this cost may increase subject to the size of the public notice advert

Min. 6 weeks

Road closure / TTRO from 5 days to 18 months

Between 5 days - 18 months

£1,200.00*

*plus advertisement cost of approx. £1100.00 - Please note this cost may increase subject to the size of the public notice advert

Min. 6 weeks

Emergency road closure / TTRO

Emergency closure / TTRO

£550.00

Within 2 hours

Extension to Temporary Traffic Regulation Order

Extension to closure / TTRO

£350.00*

*plus advertisement cost of approx. £1100.00 - Please note this cost may increase subject to the size of the public notice advert

 