The table below lists the planned surfacing of roads during June – December 2026. Further details of planned resurfacing and lining locations will be provided once confirmed for the 2026-27 financial year.

Please note that this programme is subject to change at short notice as these activities are weather dependent.  

Full details for each location listed below can be found online at one.network.  

Local residents and businesses affected by these works will be notified closer to works commencing. If there are any changes to dates (due to weather) a further letter will be sent to residents to let them know.

Advanced warning signs will be in place at both ends of the scheme of works; any changes to dates (due to weather) will be reflected on the advanced warning signage.

Scheme Name

Scheduled month for completion 

Detail of work to be completed

Ward 

Carriageway resurfacing

Wolverhampton Road East 

September/October

Surface Dressing and lining

Blakenhall 

Scheduled Schemes

Significant progress has been made in improving roads and safety across Wolverhampton during this year.

This table details work due to be carried out across the Highways Capital programme:

  • Footway programme
  • Highways Structural Maintenance work
  • Road Safety Improvements
  • Safer Routes to School
  • Carriageway Surface Treatment
  • Carriageway Resurfacing
  • Streetlighting programme
  • Intelligent Transport System Projects

Our approach to road improvements is firmly data driven as set out in the Highway Asset Management Strategy and capital programmes. We use a combination of advanced condition surveys, AI, public feedback, and complaints data to prioritise works, ensuring that investment is targeted where it will have the greatest impact.

Scheme Name

Scheduled month for completion 

Detail of work to be completed

Ward 

Highways Structural Maintenance work

Oxley Moor Road

TBC

Culvert repair design, following completion of trial holes

Oxley

Deans Road 

TBC

Pre works meeting with contractor to carry out brick work and mortar repairs

Heath Town/East Park/Wednesfield South

Wightwick County Bridge

TBC

Concrete repairs. Currently in design phase

Tettenhall Wightwick

Road Safety Improvements

 

 

 

Ring Road

TBC

Local Safety Scheme. Enhanced advance signing and road markings to clearly define lane allocations and improve correct lane usage on junction approaches.

St Peters / Graiseley

Park / Blakenhall

Knox Road and surrounding roads, Blakenhall

December 2026

A proposed system of one-way roads (Consultation completed)

Blakenhall

Stowheath Lane

March 2027

Traffic calming, casualty reduction scheme

(Consultation completed)

East Park

Tettenhall Road (Chapel Ash)

March 2027

 

Pedestrian refuges, introduce right turn lanes and enhanced road markings

(Consultation completed)

Park

Prestwood Road West

March 2027

 

Provision of permanent VAS signs

Heath Town / Fallings Park

Northwood Park Area Traffic Calming

March 2027

 

Traffic calming, 20mph speed limit, casualty reduction scheme

Bushbury North

Darlaston Lane

March 2027

 

Traffic calming, casualty reduction scheme

Bilston South

Goldthorn Hill Local Safety Scheme

March 2027

 

Traffic calming, casualty reduction scheme

Blakenhall

Moseley Road / Prouds Lane 

March 2027

 

Traffic calming, casualty reduction scheme

Bilston North / East Park

Safer Routes to School 

Castlecroft Primary (Tettenhall)

March 2027

 

20mph speed limit, traffic calming, and school zones signs and road markings

(Consultation completed)

Tettenhall Wightwick

Edward the Elder (Wednesfield)

March 2027

 

20mph speed limit, traffic calming, and school zones signs and road markings

(Consultation completed)

Wednesfield South

Holy Trinity (Bilston)

March 2027

 

20mph speed limit, traffic calming, and school zones signs and road markings

Bilston South

Intelligent Transport System Projects – these are yet to be scheduled

Upcoming works

Dates to be confirmed for surfacing and lining of the following locations:

  1. Tettenhall Road (Surface dressing done - lining to be completed)
  2. Underhill Lane (Surface dressing done - lining to be completed)
  3. Vicarage Road (During 2027)
  4. Wilkinson Ave 
  5. Brierley Lane 
  6. Rose Street 
  7. Patrick Gregory Road
  8. Pond Lane 
Resident and Visitor information: What to expect during works

Full Resurfacing  

What to expect before, during and after full resurfacing

Access to frontages will be maintained and diversion routes will be put in place.

For this work to be carried out satisfactorily and on schedule we will require the carriageway to be clear of all parked vehicles during the above times. Your co-operation in this matter will be greatly appreciated.

Alternative bus route information will be available online @ nxbus.co.uk prior to commencement of works.

You should also be aware that:

  • The works will involve the use of hot bituminous material which may cause burns and stick to footwear or tyres. Please therefore avoid walking or driving across newly laid surfaces.
     
  • The process involves the use of heavy construction machinery. You are advised not to walk across the carriageway within the vicinity of works being undertaken.
     
  • Pedestrian access will be maintained but care will be needed when passing the working area, particularly near plant and machinery.
     
  • There will be raised manholes and uneven surfaces for a period.
     
  • Bin collections will take place on your normal day.

Please be aware that householders are sometimes approached by firms claiming to be Council contractors and offering to undertake work such as surfacing drives.  Please note that no contractor is authorised by this Council to carry out such work.

What is Full Resurfacing?

Resurfacing is undertaken when a carriageway reaches to end of its useful life, which is represented by deformation and significant cracking across extensive areas of the surface, which can no longer be repaired. The process involves planing off the surface courses then laying a new surface material to replace it. This process can be very expensive and time consuming, requiring significant plant to undertake the work, necessitating road closures for a number of days depending on the size of the job. The benefit of undertaking this work is that the road surface can last for 20+ years just requiring minimal maintenance.

Carriageway Surface Dressing

What to expect before, during and after Carriageway Surface Dressing works  

What is Surface Dressing?  

The roads in your area are inspected regularly by highway engineers to determine whether any maintenance work is required.  

Surface Dressing is a process that is used to extend the life of an existing carriageway by sealing the surface to prevent oxidation and moisture ingress. The process involves spraying the existing carriageway surface with a bituminous adhesive then applying small loose stone chippings onto the surface and rolling them in place. A week later any loose chipping will be swept away before applying a coating material that locks the chippings in place. This process is a quick and more cost effective than resurfacing enabling road closures for a much shorter duration than other methods. The road surface can typically last for a further 7 years following the application of this treatment.

It is a speedy, efficient and economic method of preventative maintenance, causing less disruption to traffic and keeping the network flowing.  

Main roads as well as cul-de-sacs can be surface dressed.  

Due to the nature of the process it can only be carried out in dry weather and with the correct road temperatures, therefore works are typically undertaken from April to Early September. We anticipate surface dressing works to be completed by July/August 2026.

Micro Asphalt Surface Treatment 

What to expect before, during and after Micro Asphalt Surface Treatment  

What is Micro Surfacing?

The roads in your area are inspected regularly by highway engineers to determine whether any maintenance work is required. It is important that road surfaces are sealed to prevent water ingress, and to prevent further deterioration to the existing surface. It is also important to have the correct surface texture.  

Micro Surfacing is a mixture of polymer modified bitumen emulsion, small aggregate and cement. It will seal the surface, improve surface texture and prolong the life of the road for many years.  

It is a dual application process, with the first application regulating the existing surface, and the second application gives the final surface.  

Footway Micro Asphalt Surface Treatment is the same process as carriageway Micro but its hand laid instead of machine laid. Footways are pre-patched and cleaned prior to the treatment being applied.

It is a speedy, efficient and economic method of preventative maintenance and carrying out minor reprofiling of carriageway surfaces. The process is undertaken from February to November and may be weather dependent. 

Completed schemes

List of Completed Schemes

Scheme Name

Scheme status 

Detail of completed work

Ward 

Carriageway resurfacing – Completed

Great Hampton Street

Completed

Carriageway Resurfacing

St Peters

Landsdowne Road

Completed

Carriageway Resurfacing

Bilston North

Springvale Avenue

Completed

Carriageway Resurfacing

Bilston South

Moore Street/Cross Street

Completed

Carriageway Resurfacing

East Park

Penn Street

Completed

Carriageway Resurfacing

Graiseley

Connaught Road

Completed

Carriageway Resurfacing

Park

Price Street

Completed

Carriageway Resurfacing

Bilston South

Mander Street

Completed

Carriageway Resurfacing

Graiseley

Wobaston Road/The Driveway Island

Completed

Carriageway Resurfacing

Bushbury North

Butts Road

Completed

Carriageway Resurfacing

Penn

Stafford Road/Three Tuns Island

Completed

Carriageway Resurfacing

Bushbury North

St Georges Ring Road

Completed

Carriageway Resurfacing

St Peters

Chapel Ash Island

Completed

Carriageway Resurfacing

St Peters

Westminster Avenue

Completed

Carriageway Resurfacing

Penn

Nelson Avenue

Completed

Carriageway Resurfacing

Bilston North

Jeddo Street

Completed

Carriageway Resurfacing

Blakenhall

George Street

Completed

Carriageway Resurfacing

Ettingshall

Springfield Road

Completed

Carriageway Resurfacing

Bilston North

Victoria Road

Completed

Carriageway Resurfacing

Heath Town

Old Heath Road

Completed

Carriageway Resurfacing & Surface Dress

East Park

Stowheath Lane

Completed

Carriageway Resurfacing & Surface Dress

East Park

Stafford Street

Completed

Surface Dressing

St Peters

Cannock Road

Completed

Surface Dressing

Bushbury South

St Philips Avenue

Completed

Surface Dressing

Graiseley

Mount Road

Completed

Surface Dressing

Penn

Ettingshall Road

Completed

Surface Dressing

Ettingshall

Stafford Road

Completed

Surface Dressing

Bushbury North

Tettenhall Road

Completed

Surface Dressing

Park

Steelhouse Lane

Completed

Surface Dressing

St Peters

Spring Road

Completed

Surface Dressing

Ettingshall North

Manor Road

Completed

Surface Dressing

Ettingshall North

Robert Wynd

Completed

Surface Dressing

Ettingshall South & Spring Vale

Footway programme - Completed

 

 

 

Ladymoor Road

Completed

Footway Micro 

Bilston South 

Old Heath Road

Completed

Footway Micro

East Park

Castlecroft Road

Completed

Footway Micro

Tettenhall

Dickens Road

Completed

Footway Micro

Fallings Park

Quatford Gardens

Completed

Footway Micro

Bushbury South

Woodfield Avenue

Completed

Footway Micro

Penn

Carlton Avenue

Completed

Footway Micro

Fallings Park

Mullett Road

Completed

Footway Micro

Fallings Park

Scheme Name

Highways Photo Gallery

Locking on process image 1

Locking-on process after surface dressing

Locking process image 2

Locking on surface dressing 

Locking process image 3

Locking on surface dressing 


Locking process image 4

Locking process 

Locking process image 5

Locking process 

23061