The work forms part of National Grid's ongoing infrastructure improvement programme and will be in phases up until Sunday 4 October on sections of Ring Road St Patrick's and Ring Road St David's.
Temporary traffic measures include lane closures and occasional road closures affecting movement through the Broad Street/Wednesfield Rd A4124 junction.
Queues are expected from the Ring Road back towards Waterloo Road and from Ring Road St David's towards Bilston Street island.
Queues are also expected along Wednesfield Road back To Deans Road and Stafford Road towards Five Ways.
Motorists are advised to allow extra time for journeys, follow signed diversion routes and consider alternative routes where possible during the works.
City of Wolverhampton Council's Cabinet Member for City Transport, Councillor Bhupinder Gakhal, said: "Utilities companies are responsible for more than 2 thirds of roadworks in Wolverhampton.
“While these works are essential to support and maintain critical infrastructure, we understand roadworks can be frustrating, particularly on key routes around the city.
“That is why we will be monitoring the impact of National Grid’s work to ensure disruption is kept to a minimum. Where companies fail to meet their obligations, we will not hesitate to use enforcement powers available to us, including issuing fines where appropriate.
“Our message is simple: if you're working on Wolverhampton's roads, you must do so responsibly and minimise disruption.”
The restrictions are:
Ring Road St Patrick's
Tuesday 1 September to Friday 4 September
- Right turn from Ring Road St Patrick's (anti-clockwise) onto Ring Road St Patrick's (clockwise) closed.
- Lane closures from Stafford Street to Broad Street (down to 1 lane running).
- Diversion via Ring Road (anti-clockwise), Chapel Ash Island and Ring Road (clockwise).
Ring Road St David's to Broad Street
Friday 4 September to Wednesday 9 September
- Right turn from Ring Road St David's (anti-clockwise) onto Wednesfield Road A4124/Broad Street closed.
- Lane closure in place (one lane running from the Ring Road junction to the bridge on Wednesfield Road A4124).
- Diversion via Ring Road (anti-clockwise) and Ring Road St Patrick's (clockwise).
Ring Road St David's
Thursday 10 September to Thursday 17 September
- Right turn and bus lane movement from Ring Road St David's (clockwise) onto Ring Road St David's (anti-clockwise) closed.
- Diversion via Ring Road (clockwise), Bilston Street Island and Ring Road (anti-clockwise).
Ring Road St David's
Friday 18 September to Thursday 24 September
- Lane closures from Stafford Street to Horseley Fields.
Ring Road St David's
Friday 25 September to Sunday 4 October
- Lane closures from Broad Street to Horseley Fields.
- Left Hand Turn from Horseley Fields onto Corn Hill closed.
- Diversion via Horseley Fields, Union Mill Street and Albion Street.
The restrictions are weather permitting and subject to change.
The latest National Grid work follows earlier phases along Bushbury Lane, Stafford Road, Stafford Street and The Maltings during the school holidays.
To help co-ordinate all work on our highways network, the council uses Causeway one.network which motorists can use to find out how to best plan their journey.