Planning permissions
Outline planning permission was granted in March 2007. The planning permission is subject to a number of conditions controlling the type and amount of development and requiring the submission of further details of the development for approval by the local planning authorities. Copies of the planning permissions are available to download by clicking on the pdf files at the bottom of the page.
A key requirement is that only a small part of the site (phase 1 comprising up to 15,000 m2) can be built and occupied prior to the construction of a new access to Junction 2 of the M54 motorway. This new access is the subject of a separate detailed planning permission, also granted in March 2007.
The outline planning permission is also subject to a ‘Section 106’ legal agreement that specifies a number of required planning obligations including the following:
- The improvement of highway junctions at Wobaston Road and Stafford Road
- The provision of bus services or enhanced existing bus services to serve the development
- Coordination of Travel Plans for businesses occupying the development
- Provision of a network of footpath/cycleways on the site
- Improvements to the towpath along the Staffordshire and Worcestershire Canal
- Recruitment and training initiatives
- Nature conservation compensation areas at Upper Pendeford Farm
- Provision of public art works
Contact us
Contact us to request a cd-rom containing planning application submissions, planning permissions and proposed highway junction schemes.
Download the planning permissions by clicking on the pdf files below:



|